Project Overview Sidewalks Streetlights & Streetscapes
This project will consist of demolition of existing and construction of a new, wider sidewalk with improved pedestrian lighting and landscaping to create an enhanced aesthetic experience along South Gay Street from Publix to Thach Avenue. The project is part of the City of Auburn's Downtown Master Plan.
Status
- Design
- Bid Advertisement
- Contracts
- Construction
0%
The notice to proceed was issued to the contractor March 17th, 2025 with construction beginning March 19th.
Photos




Timeline
Aug 2025
Close Out Finishes
Aug 1, 2025
Jul 2025
Construction Finishes
Jul 16, 2025
Jul 2025
Close Out Starts
Jul 2, 2025
Mar 2025
Construction Starts
Mar 17, 2025
Jan 2025
Contracts Finishes
Jan 15, 2025
Dec 2024
Contracts Starts
Dec 18, 2024
Dec 2024
City Council / AWWB Starts
Dec 17, 2024
Dec 2024
Bid Opening Starts
Dec 3, 2024
Nov 2024
Bid Advertisement Finishes
Nov 29, 2024
Nov 2024
Bid Advertisement Starts
Nov 10, 2024
Nov 2024
Design Finishes
Nov 6, 2024
May 2024
Design Starts
May 30, 2024